How Long Does a Kitchen Remodel Take? Full Timeline
"How long will we be without a kitchen?" It is the second question every homeowner asks, right after cost — and the one where contractors most often overpromise. A realistic kitchen remodel timeline in South Florida runs from about eight weeks of construction for a straightforward refresh to five or six months for a full luxury renovation with structural changes. Here is the honest phase-by-phase breakdown, including the parts most timelines leave out.
Phase 1: Design and Planning (3–8 Weeks)
Before anyone swings a hammer, your project needs finished drawings, final material selections, and a locked scope. For a design-build kitchen renovation, this phase includes space planning, cabinetry design, appliance specification, and engineering if walls are moving. Rushing it is the single most expensive mistake in remodeling — every decision made after construction starts costs more than the same decision made before. Our process on the kitchen remodeling page walks through exactly what gets decided when.
Phase 2: Permits and Procurement (4–12 Weeks, Overlapping)
Two clocks run in parallel here:
- Permitting. Kitchen remodels involving plumbing, electrical, or structural work require permits under the Florida Building Code. Municipal review times in South Florida vary widely — some cities turn permits in two to three weeks, others take six to eight, and condo association approvals add their own layer. A contractor who "doesn't need permits" is a red flag, not a shortcut; see our FAQ for how we handle this.
- Procurement. Semi-custom cabinetry typically takes 6–10 weeks to deliver; fully custom runs 10–16. Professional appliance packages and specialty slabs can carry long lead times too.
The good news: a well-run project overlaps these with design finalization, so the calendar cost is mostly hidden — provided everything is ordered before demolition.
Phase 3: Construction (6–14 Weeks)
Once permits are in hand and materials are secured, the visible work begins. Typical sequence and durations:
- Demolition — 2–5 days, plus dust protection and containment.
- Structural changes — 1–2 weeks if walls are coming out, including beam installation and inspections.
- Rough plumbing, electrical, and mechanical — 1–2 weeks, ending in rough inspections.
- Drywall, ceilings, and paint prep — about 1 week.
- Flooring and cabinet installation — 1–2 weeks; cabinets set the pace for everything after.
- Countertop template and fabrication — the sneaky one: counters are templated after cabinets are set, then take 1–2 weeks to fabricate and install.
- Backsplash, plumbing and electrical trim, appliances — 1–2 weeks.
- Punch list and final inspections — 3–7 days.
Add it up and a same-layout renovation lands around 8–10 weeks of construction; a full kitchen renovation with layout or structural changes typically runs 10–14.
What Actually Causes Kitchen Remodel Delays
After 25+ years of combined experience, the delay list is predictable: mid-project design changes, materials ordered late, hidden conditions behind the walls (outdated wiring, corroded plumbing, prior unpermitted work — common in older Florida homes), inspection scheduling, and condo work-hour restrictions. Weather rarely delays an interior remodel — but hurricane season can affect inspection availability and material logistics, which is why experienced contractors build buffer into summer schedules. Larger combined scopes, like pairing the kitchen with a home addition or whole-house remodeling project, need a single coordinated schedule rather than stacked separate ones.
How to Keep Your Remodel on Schedule
- Finish 100% of selections before demolition — down to cabinet hardware.
- Insist on a written schedule with milestones, and weekly progress updates.
- Do not release demolition until cabinets are in production.
- Choose one team accountable for design, permits, and construction, so nothing falls between contracts.
- Plan your temporary kitchen realistically. Set up a microwave, coffee station, and refrigerator in another room before demolition day, and budget for more takeout than you expect — a household that is prepared to live without a kitchen is a household that never pressures the schedule into shortcuts.
- Respond to decisions within a day or two. During construction, small questions surface constantly — grout color, outlet placement, shelf heights — and a homeowner who answers quickly keeps trades moving instead of waiting.
Work With Xpert Construction Group
Xpert Construction Group runs kitchen renovations on clear, written timelines backed by a licensed and insured Florida contractor (CRC 1335930). Contact us for a free consultation and a realistic schedule for your project.
Plan Your Project With Florida's Luxury Construction Experts
Licensed & insured (CRC 1335930), 25+ years of experience, design-build delivery. Get straight answers and a clear plan.
Schedule a Free Consultation

